317. The construction of a surface water withdrawal facility is eligible for a declaration of compliance on the following conditions:
(1)  the facility is not situated in a meander or a zone subject to erosion or the accumulation of sediments and alluvial deposits;
(2)  any work required to stabilize the littoral zone or a riverbank or lakeshore, as the case may be, does not exceed an area of 16 m2 for a dry hydrant, or 4 m2 in other cases.
O.C. 871-2020, s. 317.
In force: 2020-12-31
317. The construction of a surface water withdrawal facility is eligible for a declaration of compliance on the following conditions:
(1)  the facility is not situated in a meander or a zone subject to erosion or the accumulation of sediments and alluvial deposits;
(2)  any work required to stabilize the littoral zone or a riverbank or lakeshore, as the case may be, does not exceed an area of 16 m2 for a dry hydrant, or 4 m2 in other cases.
O.C. 871-2020, s. 317.